Station Name: CONWIL

[Source: Nick Catford]


Date opened: 3.6.1860
Location: East side of A484
Company on opening: Carmarthen & Cardigan Railway
Date closed to passengers: 22.2.1965
Date closed completely: 22.2.1965
Company on closing: British Railways (Western Region)
Present state:

The stationmaster's house is in private occupation. Both platforms are extant, although overgrown. Foundations of the station building and the pit of the signal box can still be seen on the down platform when the undergrowth is cleared. The weighbridge office in the goods yard is still standing - the yard does not belong to the Gwili Steam Railway.

County: Carmarthenshire
OS Grid Ref: SN386263
Date of visit: August 1967

Notes: Conwil station served the village of Cynwyl Elfed a mile to the north-west of the station. The station always used the English shortened version of the name.

Conwyll station opened as a temporary terminus of the Carmarthen & Cardigan railway when it was extended from the first temporary terminus at Carmarthen on 3 September 1860. The River Gwili was diverted to allow the station to be built which is why there is a bridge over the river at each end of the station. The first train, consisting of three carriages, made the journey in 15 minutes. Following a dispute with the SWR over the high cost of providing the service over the new line, the station closed on 31 September 1860. Having obtained their own rolling stock the C & CR reopened the station on 15 August 1861.

The February 1863 Bradshaw (reproduced below) shows 9 trains in each direction between Carmarthen Junction and Carmarthen. Only two if them run through to Conwyll, one mid morning and one mid afternoon. There was no Sunday service to Conwyll.

The line was further extended to Pencader on 28 March 1864, and Conwyll became a through station and the name was changed to Conwil. Conwil had a passing loop and two platforms. Passenger facilities were very modest, consisting of a timber station building with a pitched slate roof at the north end of the down platform; this comprised the booking office and waiting room. The two-storey stationmaster's house was alongside, just beyond the end of the platform. There were no passenger facilities of any kind on the up platform although there was, at one time, a small building of unknown purpose. There was one running-in board on each platform but no other station signs.

Watering facilities were provided at the station. Water was supplied from a small reservoir on the hillside to the north of the station (it is still there - as a pond in someone’s garden), this supplied a tank to the north of the station (over the bridge). The water was then piped back over the bridge to a water crane on the down platform. The pipe then continued underground to fill the typical GWR round metal water tank at the south end of the up platform. The cast iron water pipes are still on the bridge and there was a valve half way across the bridge which can still be seen.

Conwil signal box was located on the down platform at the south end of the station building. It controlled access to two sidings, both on the down side. The up starting signal was very unusual being a GWR lattice design; there are only about 30 of these made. The main goods yard was to the south of the station with the other siding to the north. The good yard included a timber goods shed with a pitched slate roof, 2-ton crane, cattle dock and pens. There were two huts near the cattle dock, one housed a mechanical trolley and the other was the shed for the Conwil to Llanpumpsaint permanent way gang. The goods yard closed on 2 December 1963 and was leased to a tarmac dealer between 1965 and 1973.

After closure to passengers in 1965, the loop was lifted and the station buildings were demolished. After complete closure of the line in 1973 the remaining track was lifted in 1975. Shortly afterwards, the trackbed between Abergwili Junction and Llanpumpsaint was sold to the Gwili Steam Railway. Some restoration work has been done at Conwil other than clearing the undergrowth from time-to-time. Both platform walls were rebuilt in the 1980s from the ground up by the Manpower Services Commission. The Gwili Steam Railway eventually intends to extend its line from the present northern terminus at Danycoed Halt to Conwil, but extension southward to Carmarthen is the priority. There are two bridges over the River Gwili between Danycoed and Conwil that require expensive repairs, so the extension to Conwil is still some years away.

BRIEF HISTORY OF THE CARMARTHEN & CARDIGAN RAILWAY
In 1845 there was a proposal to build a branch line from Carmarthen to Cardigan at the mouth of the River Taf as part of the planned Great North and South Wales & Worcester Railway; nothing came of this scheme. The South Wales Railway opened its broad gauge line from Chepstow to Swansea in 1850, extending to Carmarthen in 1852 with the intention of eventually reaching Neyland.

The Carmarthen & Cardigan Railway Company was formed in 1854 to promote a broad gauge railway from a junction with the SWR at Carmarthen. Initially the line would terminate at Newcastle Emlyn, a distance of 26¾ miles, later to be extended 12 miles to Cardigan where the company intended to build a deep-water port.

The Carmarthen & Cardigan Railway was incorporated by an Act of 1 July 1854 to build the line between Carmarthen and Newcastle Emlyn. There was authorised capital of £300,000 with powers to borrow a further £80,000. City of London-based contractor John Jay was employed to build the line. Jay's previous railway contracts included Stoke-on-Trent railway station, and a section of the Great Northern Railway north of King's Cross together with King's Cross goods station and passenger terminus; these were all built around 1850.

The line was to be constructed in two stages, with the first 18-mile section linking Carmarthen and LLandyssil. Work started a mile south of Carmarthen following the ‘turning of the first sod’ in March 1857; a junction was made with the South Wales Railway at Myrtle Hill. The main engineering obstacles facing engineer Joseph Cubitt were the construction of a crossing over the River Towy at Carmarthen and the excavation of a tunnel between the valleys of Skanda Vale and Dolgran, under the Brechfa Forest south-west of Pencader.

During construction in 1859, the C & CR attempted to switch from broad gauge to standard gauge, which would have meant that all railway infrastructure could be built to smaller (and thus cheaper) dimensions. Such a change would require the approval of Parliament, and pressure was put on the company by the South Wales Railway which did not want the rival standard gauge making an incursion on its territory; a Bill authorising this change of gauge was never put before Parliament.

The first mile to a terminus at Carmarthen opened on 1 March 1860 after which progress north was rapid, with Conwil station opening on 3 September 1860.  At this time, the C & CR owned no rolling stock so they had to rely on the SWR to provide the service. This created tension between the two companies owing to excessive charges being levied and, as a result, the
service was suspended on 31 December 1860. The company then hired two 4-4-0 tank engines and reopened the line with its own rolling stock on 15 August 1861. In October 1861 Bronwydd Arms, a new station between Carmarthen and Conwil, first appeared in company timetables.    

Progress north now slowed owing to problems during the construction of the 895yd Pencader tunnel (also known locally as Alltwalis Tunnel and Dolgran Tunnel). The digging required two construction shafts which could then be used for ventilation. Construction started in the spring of 1857, and digging initially proceeded from four sites - at either end and from the bottom of both ventilation shafts. Work was expected to be completed by December 1860/January 1861.

The tunnel was 'finished' in March 1861 although, at that time, it was exposed rock without a brick lining and required further work to complete it. The long approach cuttings were also unfinished. During construction of the tunnel, many of the horses used to haul away excavated rock died from disease and were buried in the field surrounding the northern of the two shafts. The same field also has grassed-over rubble remaining from cottages built by the construction navvies. Much of the spoil excavated was used to build embankments north and south of the tunnel, but large spoil heaps can still be seen on the hillsides around both ventilation shafts.

Further delays were caused by the original contractor, John Jay, abandoning the construction of the line in autumn 1861. By November, however, another contractor, Holdens, took over the construction.  Work was then focused on finishing several miles of railway either side of the tunnel and, although easy to the north, to the south heavy engineering of cuttings and embankments slowed progress.

The 12-mile extension to Cardigan was authorized by an Act of 1 July 1863 but it was never built.

Track is known to have been laid through Pencader Tunnel at some point prior to December 1863. An official Board of Trade inspection was carried out in January 1864, and the tunnel opened with the rest of the Llanpumpsaint-Pencader section on 28 March 1864. At that time the tunnel was still unlined, and a watchman was employed to inspect it for any rock falls until it was eventually lined with brick some years later.

The line reached Llandyssil, a further 3½ miles, on 3 June 1864 with a service of four trains in each direction, taking approximately 70 minutes between Carmarthen Town and Llandyssil. Most trains started or completed their journeys at Carmarthen Junction station.

By now the high cost of construction, especially Pencader Tunnel and the purchase of two tank engines from Rothwell & Co, had drained the company’s resources and it was forced into bankruptcy. A Receiver was appointed to run the railway without any interruption to the service. 
The tank engines were sold but were leased back to the Receiver.

In 1860 the Manchester & Milford Railway received Royal Assent to build a line from the C & CR at Pencader to Llanidloes. In 1861 a route was proposed north, mainly along the east side of the River Teifi valley from Pencader to Devil’s Bridge. There, a junction station would be constructed, with the main line proceeding to Llanidloes, and a branch line to Aberystwyth.

By late 1864 the proposed route had changed, moving west from the original plan. This would result in both a shorter route to Llanidloes, and relocating the junction station from Devil’s Bridge to a new junction station near Ystrad Meurig. Parliamentary approval for the new route, to be built to standard gauge, was received in 1865

Work on the southern section of the line progressed rapidly, and the line from Pencader to Lampeter was opened on 1 January 1866. The M & MR made a junction with the C & CR half-a-mile north of Pencader. However, because of the gauge difference the two lines didn't actually join, and a new interchange station called Pencader Junction was opened with the new line. The next section from Lampeter to Strata Florida was completed by 1 September 1866, and the final section to Aberystwyth by August 1867.

The South Wales Railway had been taken over by the GWR in 1862. By that time broad gauge was in decline and, in order to allow through running between the C & CR and the newly opened M & MR, the 13¾ miles from Abergwili Junction to Pencader Junction were altered to mixed gauge on 1 November 1866. The M & MR was given running rights into Carmarthen, but its trains were not permitted to call at intermediate stations.  The C & CR directors regained control of their line in 1867. The remainder of the line to Llandyssil was converted to standard gauge on 1 June 1872, and all broad gauge running ceased from that date.

In September 1869 the C & CR formed a new company for extending the line to Newcastle Emlyn and eventually on to Cardigan, but the proposed extension failed to get sufficient local support. An approach was made to the London & North Western Railway to buy the line and build the extension to Newcastle Emlyn, but nothing came of this.

In 1881, a Bill was put before Parliament authorising the C & CR to extend its line to Newcastle Emlyn, reduce the number of directors, and sell or lease its undertaking. On 4 March 1881 an Agreement leasing the C & CR to the GWR was approved by the House of Lords. Under GWR control the service was reduced to three down trains between Carmarthen and Llandyssil, but still four up trains The M & MR timetable of the same date showed three through trains in each direction between Carmarthen and Aberystwyth, with an extra morning service in each direction between Carmarthen and Lampeter. On 1 July 1882 the  C & CR was absorbed into the GWR.

All the necessary land for the extension was purchased by April 1885 but the GWR, who had been reluctant to build the line, ensured that work progressed as slowly as possible, taking over ten years to reach Newcastle Emlyn. The extension finally opened on 1 July 1895 with one intermediate station at Henllan. The long-awaited railway was given a riotous reception by the townspeople and traders of Newcastle Emlyn. The opening train was decorated with flags and flowers, and in the afternoon about two thousand people sat down to tea in the New Market House. In the evening a grand banquet was held in the Emlyn Arms Hotel.

A further extension to Cardigan was now ruled out, largely because of opposition to the intrusion of the line into an area of natural beauty that had become a popular tourist attraction. Consequently the GWR had to make do with a motor bus service from Newcastle Emlyn to Cardigan. A second intermediate station called Pentrecourt Platform opened on 1 February 1912.

The timetable for 1902 showed a daily service of four trains in each direction between Carmarthen and Newcastle Emlyn. On Saturdays there were two extra trains to Llandyssil only. There was no Sunday service. The M & M timetable for the same date shows four trains between Pencader and Aberystwyth, with three in the opposite direction. There was an early morning Saturdays-only train between Lampeter and Pencader, to connect with the morning Newcastle Emlyn to Carmarthen service.

The Manchester & Milford Railway was leased by the Great Western in 1906 and absorbed in 1911. Carmarthen to Aberystwyth then became the main line, with the Pencader- Newcastle Emlyn line operated as a branch. The GWR opened a branch from Lampeter to Aberayron on 12 May 1911.

The Newcastle Emlyn branch was never busy, but the new 'main line' thrived by serving the local farming and wool industries though, in the years following the First World War, this traffic gradually declined as local bus services were introduced. Between the wars the GWR provided camping coaches at several stations. The route earned a reputation as a meandering rural branch
where trains trundled along, often flagged down by market-bound farmers' wives making their way across the fields to board the carriages. In fact, nearly three hours were permitted for the 56-mile journey between Carmarthen and Aberystwyth.

The Second World War brought a new lease of life as a relief route providing a vital link for northbound traffic, with regular movements of heavy munitions to Chester. After the war the line settled back to a quieter existence.

With the ever-increasing popularity of the car, especially after WW2, the Teifi Valley lines clearly had no future under a nationalised British Railways. The Aberayron branch was the first to lose its passenger service from 2 February 1951. Passenger services lasted a little longer on the Pencader-Newcastle Emlyn branch, with the last train running on 13 September 1952. The main line enjoyed a brief resurgence in the 1950s when the Royal Train traversed the route, and other new traffic included Butlins through-specials taking holidaymakers to the new camp at Pwllheli.

By the end of the fifties, there were three weekday trains each way (four on Saturdays) with a journey time of around 2½ hours with 16 timetabled stops and another 5 request stops. Declining passenger figures meant that the Beeching Axe was inevitable; in the end, however, it was nature that struck the first blow. Heavy flooding severed the line six miles from Aberystwyth in December 1964, in the same weekend that storms caused the Ruabon to Barmouth Line to suffer a similar washout. The last passenger train ran along the truncated route south of Strata Florida on 22 February 1965; inexplicably the BR network map dated 1965 showed Pencarreg, rather than Strata Florida, as the temporary northern terminus. The line remained open for freight using Hymek locomotives until around 1970, then by Class 37 locomotives. Despite closure to passengers, the branch lines also remained open for freight traffic. Withdrawal of freight facilities at individual stations started in December 1963. By 1965 freight-handling had ceased at all stations except Lampeter and Newcastle Emlyn, which then became railheads.

Scheduled for complete closure at the end of 1972, the Newcastle Emlyn branch received a number of reprieves. The Teifi Valley Railway Preservation Society was formed in October 1972 with the intention of purchasing the Carmarthen-Newcastle Emlyn section for the operation of a steam-hauled tourist passenger service. Special excursion trains were chartered from British Rail giving hundreds of people their first opportunity of travelling on the line and seeing for themselves the outstanding countryside through which it passed.

Negotiations were opened with British Rail for the purchase of both land and track, and a stay of execution was obtained on the lifting of the line. However, the enthusiasts were faced with two insurmountable problems. Month by month the price of the track increased, frequently by tens of thousands of pounds, only to be aggravated by a serious shortage of steel, which put railway track at a premium. The second problem was the lack of local interest and support. Although offers of help poured in from all over the country, local working parties rarely attracted more than a dozen-or-so people, from a total membership of 200. 

The end came in 1973 for both the Newcastle Emlyn branch and the main line from Carmarthen to Lampeter with the end of the milk traffic. The last passenger train over both lines was the RCTS Farewell to the Teifi Valley Milk Branches railtour on 30 December 1972.

The freight that kept the main line open was dominated by milk traffic between Carmarthen and Lampeter, where trains were routed to the last remaining part of the main line to Aberystwyth as far as the creamery at Pont Llanio near Llanddewi-Brefi which survived until 1970; they also used the Aberayron branch as far as the creamery at Green Grove near Felin Fach, which
remained in service until discontinued by British Rail in 1973; this resulted in the final closure of the line. Track was left in place until the summer of 1975.

Two years after its closure, the Gwili Railway Preservation Company was formed with the ambition to preserve at least eight miles of track of the former route, from Abergwili Junction along the Gwili Valley to the station site at Llanpumpsaint.

Track-lifting had already started by the time of the formation of the new company and, as a result, only a mile of track north of Bronwydd Arms was left in situ. The Company was, however, able to acquire the full eight-mile stretch of trackbed from Abergwili Junction to Llanpumpsaint for both rebuilding and preserving. Over time the railway has extended the operational length from one mile to 2½ miles, with its current northern terminus at Danycoed.

The society is currently focusing its attention on a southward extension towards a proposed Carmarthen North station. Since the preservation society owns the trackbed as far as Abergwili Junction, two miles south of Bronwydd Arms, a new station can be constructed alongside the new Carmarthen eastern bypass. This will, hopefully, greatly improve visibility of the railway to passing traffic on this busy road compared to the less conspicuously sited Bronwydd Arms station. Once the southern extension of the Gwili Railway is complete, it will increase the length of the route to around 4½ miles.

Reconnection with Carmarthen railway station is currently impossible as the bridge that once carried the line over the River Towy was demolished in the 1980s.

Although attempts to preserve a standard-gauge line to Newcastle Emlyn were not successful, a restoration project eventually got under way in 1981 when a group of enthusiasts bought part of the trackbed at Henllan.  In 1983, with the help of funding and labour from the Manpower Services Commission, they laid a 2ft-gauge track from Henllan to Pontprenshitw, where passengers were invited to take a short walk to admire the waterfall under the railway bridge.

In 1987 the Teifi Valley Railway was extended as far as Llandyfriog and, since 2006, has been further extended to the current end of the line at Llandyfriog Riverside. During spring 2009 work proceeded to re-site Henllan station to its original location on the opposite side of the road. This new platform was brought into use in July 2009.

Tickets from Michael Stewart, Bradshaws from Alan Young & Chris Totty, Route map drawn by Alan Young

Sources:

See other stations on the Carmarthen & Cardigan Railway: Carmarthen Junction, Carmarthen 1st, Carmarthen 2nd STILL OPEN, Bronwydd Arms, Llanpumpsaint, Pencader, Pencader Junction, Llandyssul,
Pentrecourt Platform, Henllan
& Newcastle Emlyn


A southbound passenger train from Aberystwyth approaches Conwil station in July 1956. All the stations on the southern section of the Aberystwyth line between Carmarthen and Pencader, except Bronwydd Arms, had passing loops and two platforms. There were also watering facilities at Conwil: a water crane is seen at the end of the platform. A water tower and crane were at the south end of the up platform. The stationmaster's house is seen behind the modest station building. The signal box controlled access to the goods yard, with a siding at both ends of the station.
Copyright photo by HC Casserley


1906 1:2,500 OS map. The station had two sidings, both on the down side. The main goods yard, which included a timber goods shed, 2-ton crane, cattle dock and pens, was to the south of the station; the other siding is seen to the north of the station. Access to both sidings was controlled by a signal box on the platform adjacent to the station building at its south end.

Conwil station looking north-west from the up platform in July 1956. There were no
facilities on the up platform.
Copyright photo by HC Casserley

A southbound passenger train from Aberystwyth pulls in to Conwil station c. 1950s.This Churchward-designed, 43xx 2-6-0 No 6375 entered service in July 1921 on the GWR. Built by Robert Stephenson and Co, this loco had a service life of over 42 years when it was withdrawn from 87G, Carmarthen shed, in September 1963 to be scrapped by Cohens of Morriston in March 1964. Originally built with inside steam pipes, this was one of the later locos to be converted to outside pipes by BR in October 1948.
Photo from John Mann collection


Conwil station looking south-east from the down platform c. 1950s. Note the typical GWR round water tower and crane at the end of the platform.
Photo from John Mann collection

Conwil station in June 1962 seen from the 5.50 p.m. train from Carmarthen to Aberystwyth. On this occasion no passengers alighted or boarded at Conwil.
Looking south-east towards Conwil station in June 1963. The stationmaster's house is seen on the right.
Photo received from Gwili Steam Railway

Conwil station looking north-west from the down platform c. 1960s.
Photo from John Mann collection

Conwil station looking north-west in September 1967, 2½ years after the station closed to passengers. After closure the passing loop was quickly lifted, but the redundant water tower was left in
place at this time.
P
hoto by Nick Catford

Wirral Railway Circle Heart of Wales Land Cruise passes through Conwil
station on 9 December 1972.
Photo received from P G Wright

Conwil station looking south-east in April 1975 about  two years after complete closure of the line. All the station buildings have been demolished, and track-lifting was to start within a few months.
Photo by John Mann

Conwil station looking north-west in April 1975 about two years after complete closure of the line.
Photo by John Mann

Conwil station looking north-west from a similar viewpoint to the first picture. The stationmaster's house is still standing, but the station building and signal box have gone without trace.
Photo by Jeremy Evans


Last updated: Wednesday, 17-May-2017 09:18:42 CEST
© 1998-2012 Disused Stations