Station Name: GRANGE COURT JUNCTION

[Source: Darren Kitson]


Date opened: 1 June 1855 (an exchange platform is thought to have existed by 1853 - see text
Location: East side of Grange Court Road
Company on opening: Hereford, Ross & Gloucester Railway and South Wales Railway
Date closed to goods 12 August 1963 (a private siding remained available thereafter)
Date closed to passengers: 2 November 1964
Date closed completely: 2 November 1964
Company on closing: British Railways (Western Region)
Present state:

A fragment of the former Down Platform with building thought to have been a toilet block survives along with the station house

County: Gloucestershire
OS Grid Ref: SO726162
Date of visit: Not visited

Notes: Some seven miles south-west of Gloucester in the Parish of Westbury-on-Severn lies the village of Northwood Green. The 2021 Census gave the population of the village as 712, this figure including residents of Grange Court Road to the south of the main part of the village and south of the railway. At the time the railway arrived the village was little more than a scattering of buildings amongst woodland. The farmhouse that is Grange Court lies to the south-east of the village and at the time the railway arrived would have been the prominent landmark, hence the naming of the station after it with, perhaps, some input from the landowner of the time.

Grange Court Junction, as the station was always named, was an elaborate affair for what was in essence little more than an interchange between the two original railway companies and their successors the Great Western Railway and British Railways. It lay to the west of the point of divergence of the lines to Hereford and South Wales, a situation which resulted by necessity in the provision of four platforms; one side platform for Up trains from Hereford; an island platform for Down Hereford and Up main line trains (the South Wales Railway); one side platform for Down South Wales trains. On the latter platform was the main building, with waiting and staff facilities on the island platform and a simple waiting room on the Up Hereford platform. All buildings were stone with quoins and all were provided with canopies. The roof of the building on the island platform and only this building had the ends of its spandrels hidden by Grotesques but why this was done remains a mystery. There were originally a total of twelve Grotesques but as the years marched on many disintegrated or disappeared entirely as is evident in photographs. All platforms were linked by a covered footbridge. Originally the railway through Grange Court Junction was to the Great Western Railway's broad gauge (7ft 0¼in) as was usually the case with smaller companies who were on good terms with the Great Western. If maps are to be relied upon, the Up Hereford platform and waiting room along with the footbridge were provided at a later date; these features were not shown on the OS 6in map of 1879 but were present on the 1901 edition to the same scale. 

The September 1926 Great Western Railway timetable for the Grange Court - Hereford line and the alternative route via Newent. It will be noted that at this time not all trains called at Oakle Street. The Ledbury line branched off at Over Junction, just west of Gloucester and was a somewhat meandering rural branch line with the only intermediate place of any note being Newent. For the final decades of its life an autotrain or GWR diesel railcar was adequate. The line closed to passengers in 1959. Passengers travelling between Gloucester and Hereford or vice versa via this route needed to change trains at Ledbury.

Grange Court Junction goods yard was immediately east of the station and on the Down side of the railway. The yard could handle all classes of traffic and was provided with a 1½ ton crane but, oddly, appears to have never been provided with a goods shed. Perhaps because the station was primarily an interchange facility, goods traffic was not catered for until sometime in the early 20th century. Mail, parcels and sundries would be dealt with at the station as was the norm. West of the station and in the 'V' formed by the diverging routes further sidings gradually appeared. These were private sidings serving various industries which occupied the site at different times. The earliest known was the Albion Carriage & Wagon Works. This company is known to have produced many coal/mineral wagons but went out of business in 1903; perhaps being a small company it struggled to compete with the much larger and better known Gloucester Railway Carriage & Wagon Company which started out in 1860. Among subsequent occupiers of the Albion site was Christie & Vesey Ltd. who had fingers in many pies but were much involved with timber and had a wharf at Charlton, SE7 as well as other premises across the country. Companies House (an agency of the British Government) records the firm as being Dissolved on 12 December 2022

Signalling at Grange Court Junction is a story in itself. Originally there was an East and West 'box, both of which were later replaced and repositioned only to be replaced in 1935 by a single 'box on the Up side at the Gloucester end of the station. The original West 'box was a strange affair, being immediately adjacent to the road bridge and on its east side but towering above it for sighting reasons. It apparently had no windows and resembled what we would today call a 'bird hide'. The original East' box stood a distance east of the station and on the Down side of the railway. No technical details of the original East 'box are known but its West counterpart was a GWR Type 1. Both 'boxes opened circa 1869 and both closed in 1896. The second East 'box was a GWR Type 5 with 39-lever frame, the second West 'box being of the same type but with a 32-lever frame and both were abolished on 17 April 1935 when the single replacement was commissioned. This, the fifth and final 'box at Grange Court Junction, was situated on the Up side of the line at the east end of the station. It was a GWR Type 31 and originally fitted with the GWR Type VT3 68-lever frame. On 25 July 1954 the 'box was fitted with an IFS (Individual Function Switch) panel. This in turn was replaced on 24 March 1957 with further alterations occurring in June 1964. Fitted with detonator placers, this signal box closed on 2 June 1969 with control passing to Gloucester, Grange Court by this time having ceased to be a junction insofar as passenger traffic was concerned. Crossovers on the main line were retained for emergency use, east of the former station and remained at the time of writing.

An extract from the September 1926 timetable for the Down South Wales line. Table 115 was lengthy and it is only practical to show a sample page here. It was actually a summary timetable, including trains to Hereford via Ross-on-Wye did not showing intermediate stations, Ross excepted, between Grange Court and Hereford. A bold 'M' in columns indicated "Rail Motor Car"; either a steam railmotor or autotrain among which was the service as far as Newnham. One of these was a Saturdays Only service from Grange Court. Also shown is the famous 'Chalford Motor' which locally went by a number of different names. This was withdrawn on and from 2 November 1964, the same day Grange Court officially closed, with the intermediate halts and some stations closing at the same time. The bold 'N' in the column for the 6.37pm from Cheltenham indicated via Newent (see Table 120).

At some point in time, probably during the 1930s, the station's original wick lamps were replaced and Tilley 'Challow' lamps installed. For this purpose concrete lamps posts were provided complete with the necessary winching apparatus. These 'Challow' lamps remained in use until the station closed. Therefore the Grange Court Junction platforms at least were never illuminated by electricity. For more information see a feature on Tilley Lamps on this web site

Passenger services on the line to Hereford (Rotherwas Junction) ran for the last time on Saturday 31 October 1964 with the official closure date being Monday 2 November 1964. The final stationmaster was Mr Frank Curtis. With the reason for the existence of Grange Court Junction station now gone it closed to all traffic at the same time, the date the private siding was officially taken out of use being unknown. To the east of the station was and still is (2025) a Down loop while an Up loop, also extant in 2025, more or less follows the course of the former Up Hereford line. A goods train continued to trundle as far as Ross-on-Wye until this was officially withdrawn on and from Monday 1 November 1965 and with this Grange Court ceased to be a junction for any traffic.

Grange Court Junction stationmasters:

What follows is a list of stationmasters that are known, details being obtained partly from census records and partly from various other sources.

The 1871 Census recorded a Joseph Williams as stationmaster, living with his wife Cecilia and children Robert and Anna. The 1881 Census recorded a Thomas Pearson was stationmaster, living with his wife Sarah. The 1891 Census recorded a Thomas Bailey as stationmaster, living with his wife Mary and their sons Archibald and Hugh.

Thenceforth and timelined as known:

  • Until 1896 T. Bailey
  • Until 1899 W. Roberts
  • Until 1900 W. Vaughan
  • Until 1915 Mr Fay
  • Until 1932 Mr Kirk
  • Until 1945 Mr Fletcher
  • Until 1950 Mr Freeman
  • Until 1957 Mr Lewis
  • Until 1961 Mr Howell*
  • Until closure in 1964 Frank Curtis

* Mr Howell received a back injury as a result of a derailment during engineering work sometime around 1960 - 1961. Whether he returned to his duties or the injury brought an end to his railway career is not known but '1961' may imply the latter.

THE HEREFORD & GLOUCESTER EAILWAY
The Hereford, Ross & Gloucester Railway Act 1851 was passed by Parliament on 1 June that year. Construction of the single track broad gauge line was, for the time, fairly slow being hindered by poor weather and the need for heavy engineering which included four tunnels and three bridges crossing the River Wye, or four if that north of Rotherwas Junction is included. Construction was overtaken by events for on 6 December 1853 the Newport, Abergavenny & Hereford Railway had opened its line, built to standard gauge and sowing the seeds of what would become Rotherwas Junction. The Hereford, Ross & Gloucester Railway opened on 1 June 1855, the same day as Grange Court Junction station, with trains running over mixed gauge track between Rotherwas Junction and Hereford Barrs Court (the present Hereford station, the suffix having long since been dropped). Route mileage between Grange Court Junction and Hereford Barrs Court was 22½ and from Gloucester Central 30. The route was partly through the Wye Valley and partly through the Forest of Dean

The line was amalgamated with the Great Western Railway on 29 July 1862 but by this time the writing was on the wall for the Great Western's broad gauge and in 1864 the decision was taken to convert from broad to narrow gauge. 'Narrow gauge' was a commonly used term at the time for what is now known as 'standard gauge' or less commonly 'Stephenson gauge', 4ft 8½in. Conversion had to be planned on an individual line basis in accordance with circumstances while minimising disruption to traffic and conversion of single track lines posed a particular problem in respect of disruption. In the case of the Hereford, Ross & Gloucester the line closed for conversion on 15 August 1869 with road transport substituted. The line was divided up into four-mile sections and then subdivided into quarter-mile sections, each entrusted to a gang of twenty or so platelayers who were able to complete their sections in about four hours. A broad gauge train dropped the gangs off at the various points along the line and then travelled to the end of that day's section. At the end of the day a narrow gauge (standard gauge) train would pick the men up and travel to the point where the broad gauge train had stopped, the process being repeated the next day. Obviously the task was highly labour intensive with most of the work being done with hand tools and no small degree of the proverbial elbow grease. The work was completed in just five days, a very creditable performance for the time.

Table 113 from the 1959 - 1960 British Railways Western Region timetable. By this time the option to reach Hereford via Newent had gone, this line having closed to passengers on 12 July 1959. There has however been a small increase in service frequency although it is worth noting that some trains called at all stations and halts, some did not and others called at certain places to set-down upon notice being given to the guard at various places. Given that trains were still predominantly steam-hauled at this time and changes of train would be necessary, certain journey times between Paddington and Ross-on-Wye or Hereford were not too excessive. Today and depending upon number of stops, Paddington to Gloucester takes around two hours while Paddington to Hereford occupies a little over three hours via Oxford.

It is worth noting that the first conversion from broad to narrow/standard gauge reputedly occurred in 1868 when to accommodate the Pembroke & Tenby Railway's trains the Great Western converted one line of its double track route to narrow/standard gauge. This was the section between Whitland and Carmarthen. The conversion, which meant operating as two single track lines, was ready on 1 June 1868. It was of course an interim measure and whether a true conversion is a matter of opinion.

Halts were later provided at Blaisdon, Weston-under-Penyard and Backney. Of these only Blaisdon had something resembling a proper platform, the other two being wooden affairs perched on embankments such was the topography the line passed through.

One mystery remains. Quick, 2023 revision Page 216 makes mention of an entry in the October 1853 Bradshaw of an "exchange platform" existing at Grange Court but with no trains calling. Quick goes on to say the platform was provided for the opening of the line to "Hopebrook" which may mean Hope Brook, i.e. Longhope. If we assume this assumption to be correct, Longhope station did not open until 1 June 1855 with the line. Therefore the exchange platform, if it actually existed, must have been for the benefit of construction workers with trains calling as required for that purpose. But why was it included in a public timetable? We will probably never know.

Details of the closure of the Grange Court Junction - Rotherwas Junction line have been given earlier and need not be repeated here.

Table 51 from the June 1964 - June 1965 Western Region timetable, the final timetable for the Grange Court - Hereford line. Compared to 1959 - 1960 the service level was much the same but with certain timings altered. Some trains still called at certain places to set down upon notice being given to the guard while others were not booked to call at Ballingham. Ballingham station was in a remote and sparsely populated area between Ballingham and Carey but much closer to the latter. On 31 October 1964 the 21:42 ex Hereford was the very last passenger train to call at Grange Court, at 22:45. The last Up and Down passenger trains crossed at Mitcheldean Road, one of four passing places on the line with the others being Fawley, Ross-on-Wye and Longhope. By 1964 of course, the Gloucester - Grange Court - Hereford passenger service was the only one serving Ross-on-Wye, the line to Monmouth and beyond having closed to passengers in 1959.

THE SOUTH WALES RAILWAY
The South Wales Railway ran from Gloucester to Neyland via Chepstow and Newport. Neyland was originally named Milford Haven, changing to Neyland then New Milford in the space of three years from its opening in 1852. In 1906 it reverted to Neyland. This Milford Haven should not be confused with the current Milford Haven station which is further west and still in use. The first section of the South Wales Railway to open to traffic was that between Swansea and Chepstow on 18 June 1850 with the Gloucester - Chepstow section, upon which was the future Grange Court Junction, opening on 19 September 1851.

However there was a problem. Engineering difficulties with the bridge over the Wye at Chepstow saw trains from Gloucester having to use a temporary station which has come to be referred to as Chepstow East. The location of this temporary station is something of a mystery, some sources claiming it was at Sedbury Lane with others claiming it was much closer to the River Wye, near to the site of the later and fairly short-lived Tutshill for Beachley Halt. Wherever it was, passengers were conveyed by omnibus, horse-drawn of course, between the two Chepstow stations until a single track over the Wye bridge was ready on 19 July 1852 when Chepstow East was closed. The second track over the bridge was brought into use on 18 April 1853.

The Great Western Railway (South Wales Railway Amalgamation) Act 1863 of 21 July that year authorised the Great Western Railway to take over the South Wales Railway and this took effect on 1 August 1863. By this time the end of the broad gauge on this particular route was on the horizon and In 1871 approval was gained for conversion, affecting all lines between Swindon and Gloucester to South Wales. In addition some 25 route miles between Swindon and Didcot required altering to mixed gauge, permitting the running of standard gauge trains between Paddington and South Wales via Gloucester and Cheltenham; this work was undertaken over several weeks in early 1872. The task laying ahead for the entire route involved conversion of, to the nearest round figure, 500 track miles (as opposed to route miles). The Up line west of Gloucester was closed on 30 April 1872, with the Down line operated as bi-directional single track and with an adequate number of passing loops provided. The service was, perhaps obviously, limited as a result. This work was completed on 12 May 1872. Conversion of the Down line was completed on 22 May 1872. The next stage was conversion of the Gloucester - Cheltenham - Swindon section, the same procedure as previously being followed. The Up line was completed on 26 May 1872 and the Down on 28 May 1872. Where mixed gauge track had pre-existed, the broad gauge rail became disused and was removed subsequently - there being no great urgency for this task. With this work complete, Grange Court Junction was now entirely served by standard gauge trains.

Another extract from the June 1964 - June 1965 Western Region timetable, this time for Down South Wales services. As previously, Table 80 ran into many pages and it has only been practical the show extracts here. Chosen are the pages showing the last trains of the day to pass through Grange Court. What might appear to be short workings between Gloucester Central and Grange Court were in fact Gloucester - Hereford trains. The very last South Wales line train to call at Grange Court was the 19:50 ex Cheltenham Spa St. James' at 20.35.

It is worth mentioning that the present Milford Haven station, at the end of a branch line, had been opened on 7 September 1863 by the Milford Junction Railway. In effect this left the main line of the South Wales Railway to Neyland as a branch from Old Milford Branch Junction, as it came to be known. Neyland was closed to goods on 2 December 1963 and to passengers on 15 June 1964. This line is now abandoned and as such is the only section of the erstwhile South Wales Railway to have been abandoned, the remainder being still very much in use.

THE END OF THE GREAT WESTERN RAILWAY BROAD GAUGE
This section is thought worth adding in order to clear up any possible confusion. Isambard Kingdom Brunel's broad gauge came to an end in May 1892 and a misleading tale goes something like "The conversion from broad to standard gauge was undertaken over one weekend in May 1892 - a fantastic feat". The problem is this tale implies the entire system was converted over one weekend and unfortunately many people have come to believe it, perhaps because the subconscious wishes to compare the Victorian age with the seemingly long-drawn-out infrastructure projects of today. In fact conversion of the broad gauge was undertaken over many years on a line-by-line basis, following granting of the necessary powers in the Great Western Railway Act 1866. Other than Grange Court - Hereford other early conversions were north of Oxford in March 1869 and Reading - Basingstoke in April 1869. All broad gauge traffic in South Wales came to an end on 11 May 1872 with standard gauge services commencing later that same month as mentioned previously. The final section of the Paddington - Bristol route was converted in April 1875 but this was by the installing of a third rail for the standard gauge, in other words conversion to mixed gauge. Numerous other sections of various routes were mixed gauge and full conversion merely meant the abandonment of the broad gauge outer rail. For the obvious reason, the common rail was always that adjacent to station platforms.

The final broad gauge route to be converted was Paddington - Penzance and it was this which took place on the weekend of 21 - 22 May 1892. Existing sections of mixed gauge track eased the task somewhat but nevertheless some 4,700 men were involved in the conversion work that weekend. While Brunel's broad gauge was not in itself a failure in that it could carry heavier loads and was more stable (broad gauge stock being obviously wider but not significantly higher than the standard gauge stock of the time), the problem was other companies were building their lines to the standard gauge. It is worth adding, perhaps in defence of Brunel, that at the time of inception of the GWR broad gauge in the 1830s the standard gauge was by no means 'standard' and other British lines were initially built to various gauges.

Another extract from the June 1964 - June 1965 Western Region timetable, this time for Up South Wales services. The last Up train to call at Grange Court was the 17:45 ex Cardiff General at 19:25. Given that Grange Court was supposedly an interchange station, looking at timetables through the years the station was not especially well served by South Wales line trains, making the authenticity of 'interchange' somewhat dubious. Caldicot Halt, seen in the above timetables, is worth a mention. It opened in 1932 in the form of a typical GWR wooden halt with 'pagoda' shelter on one platform. Despite being very close to Severn Tunnel Junction station it survived the cull of such halts and remains open today. The Halt suffix was however dropped in 1969 and it now has 'proper' platforms with omnibus-style shelters, platform bench seats, information screens and ticket machines.

The final broad gauge passenger train out of Paddington was the 5pm to Plymouth via Bristol on Friday 20 May, hauled by 4-2-2 locomotive Bulkeley* as far as Exeter where Iron Duke* took over. Locomotive Bulkeley returned to Paddington with the Night Mail arriving considerably late at 5.30am on Saturday 21 May. This was the final Up broad gauge service. All that then remained was to move stock to Swindon, where some fifteen miles of sidings had been specially laid, for scrapping or conversion. This was not quite the end however as a couple of isolated lines, nothing to do with the GWR, retained the broad gauge and one of these was the Holyhead Breakwater line, finally converted in 1913. On the Azores island of São Miguel a harbour line at Ponta Delgada, built to Brunel's gauge and using British built locomotives continued in use as later as circa 1970. At the time of writing two of the locomotives were believed to be still in existence. Finally a taste of the broad gauge can be had at the Didcot Railway Centre where the broad gauge has been recreated with a short running line.

*These were Rover class locomotives considered by the GWR as 'Renewals'. As Daniel Gooch's Iron Duke class were withdrawn Gooch's successor Joseph Armstrong embarked upon a policy of replacing them with near-identical locomotives, with the original names reused. Two of these locomotives had actually been built before their Iron Duke class predecessors were withdrawn, the names being transferred subsequently. While there were variations among the Iron Duke class, frame length and wheel diameters most notably, the Rover class was very much to a standard design. The last three of the Rover class did not appear until 1888, these being Great Western, Prometheus and Tornado. Of those Great Western hauled the final Cornishman out of Paddington, the 10.15am departure. The GWR had of course numerous classes of broad gauge locomotives, ranging from the downright odd-looking to the majestic. The Iron Duke and Rover classes have over time come to be the classes most people associate with the broad gauge from photographs. One exception to the 'Renewal' programme was Iron Duke class Lord of the Isles.

Tickets from Michael Stewart, Route map drawn by Alan Young

Click here to read what some local papers said about the closure

Sources and bibliography:

Grange Court Junction: Gallery 1
11 May 1872 - Early 20th Century

It is 11 May 1872 and gauge conversion work is about to get under way on the South Wales line. Of the three men in the foreground two are believed to be Mr Lancaster Owen, Assistant Divisional Engineer, and Mr J. W. Armstrong, Divisional Engineer, who were in charge of the operation. Presumably, going from the attire, these two men at those on the left and in the centre. Nothing is known about the third but his presence with the other two might suggest he was somebody in authority, a foreman perhaps. The track is that most familiar in photographs; Baulk Road with bridge rail affixed to longitudinal baulks and cross ties maintaining the gauge. Brunel's original method was to have the baulks supported on piles driven into the ground and unsurprisingly this proved wholly unsatisfactory. As familiar as Baulk Road may be, the GWR broad gauge used other types of track including chaired bullhead rail on transverse sleepers. Upon conversion to standard gauge much Baulk Road remained, the relatively simple expedient of moving the outer rail being used. Grange Court Junction station may be seen through the arch on the right but at this time the Up branch (from Ross and Hereford) platform had yet to appear. Note the slotted post signal on the left, probably newly installed. This is the only photograph which has come to light showing the original West signal box, here seen towering above the bridge for sighting purposes. It appears to have unglazed windows but whether this was indeed the case is not known. The tracks are, from right to left, Down South Wales, Up South Wales, siding, Hereford branch of which the latter appears to be hidden under piles of clutter. One little quirk worth mentioning concerns the St. Ives branch in Cornwall. This line opened on 1 June 1877, five years after the line through Grange Court was converted to standard gauge, and was the final line to built using Brunel's broad gauge. This came about because the line to Penzance was destined to be the final
conversion in May 1892.
Photo courtesy Great Western Trust Photo Archive



This rather poor quality plan from 1870 gives an idea of the track layout at the time along with mileages from Paddington via Stonehouse. The Up Hereford platform had yet to be shown as had the loop on the Down Hereford line. The original East and West signal boxes are shown but not labelled as such.
Click here for a larger version.

The OS 6in map surveyed in 1879 shows Northwood Green as a mere scattering of houses and cottages amongst woodland. The Junction Inn can be seen at its then location north of the railway. Grange Court, after which the station was named, can be seen right of centre. The Up Hereford line platform and loop had yet to appear as had any form of buildings in the 'V' formed by the divergence of routes. The original East and West signal boxes may be seen. Note at the entrance to the goods yard a weighing machine and hut are indicated, features which would later disappear. The mileage, 121 from London, was and still is via Swindon and Stonehouse. Click here for a larger version

The 1899 1:2,500 OS map shows the station had gained the Up Hereford Platform, its loop and an expansion of sidings. The second East and West signal boxes are marked as are the yard crane and cattle pen. No longer marked is the weighing machine although the hut is still there. It is thought that provision of the Up Hereford platform coincided with provision of the station footbridge. The Albion Carriage & Wagon Works has now appeared. This outfit was liquidated in 1903 and the site subsequently occupied by various other businesses. Fast forward to the time of writing and it was occupied largely by Severn Valley Woodworks but satellite imagery suggests none of the original buildings survive.

The OS 6" revision of 1901 shows Northwood Green had grown little despite the presence of the railway. At the station goods yard the weighing machine hut has now disappeared. Church Lane Crossing was controlled by a ground frame; today (2025) the crossing keeper's cottage is extant as is the trackbed on the west side of the road. Westbury Crossing is now AHB (Automatic Half Barrier) and the cottage now longer exists. Both crossings were on Church Lane and the title "Westbury Crossing" was no doubt used to avoid confusion. The village of Westbury-on-Severn is about one mile south-west of the level crossing and between 1928 and 1959 was provided with a halt served by a railmotor or autotrain between Gloucester and Newnham ('Autotrain' is GWR/BR(W) parlance for a Pull & Push train). Westbury-on-Severn Halt was perched on the embankment between the bridges over the A48 and Westbury-on-Severn Road. Access to the halt was via the latter and today is a Network Rail access point.

The OS 1:2,500 revision of 1922 shows a few changes. Northwood Green is showing signs of becoming more populous and Frocester House now stands where the original Junction Inn once stood. If maps are to be relied upon (it is not always so with revisions) the former inn became Frocester House. The second Junction Inn can be seen on the west side of Grange Court Road, south of the railway where it remains today Click here for a larger version

This was the cartographical scene in 1972, eight years after the station closed and nine years after the goods yard closed. The station house is marked as is the surviving part of the building which stood on the Down South Wales platform. Oddly the former weighing machine hut has reappeared or, more likely, another hut has appeared in its place. It will be noticed that the houses of Northwood Green, are named. Northwood Green is famous for this (or infamous if you happen to be a delivery driver), residents preferring names to numbers even though numbers are allocated.

Just west of the station on 11 May 1872 poses a gauge conversion train. The men are determined to be in the scene, with all vantage points apart from on the locomotive being utilised. In 1872 having a photograph taken was still something of an occasion. The train is sitting on the Up side siding and the 0-6-0 locomotive appears to be a 'Standard Goods' with later design of cab. Of interest are the signals which are of the 'Disc & Crossbar' type. There was a disc mounted above the crossbar and set at a right angle to it, but for whatever reason the discs are invisible in this photograph. However, the man standing atop the signal to the left of the other appears to have his left hand resting upon the disc. Another possibility is the discs having been removed as part of the replacement of these signals and the presence of an apparently new slotted post signal in the other 1872 photograph may suggest this was the case. These Disc & Crossbar signals rotated through 90° in the horizontal plane; if the disc faced a driver it indicated 'clear' or in the parlance of the time 'All Right' or 'All Is right'. On the other hand if the crossbar faced a driver it meant 'stop' or 'All is not right'. Both crossbar and disc were perforated to make them less vulnerable to the wind. During the hours of darkness oil lamps were used, two of which can be seen on the signal to the right. These lamps were also set at 90° to each other and operated by the same method as the disc and crossbar. The arrow-like device is a 'Fantail' signal, the purpose of which was to advise 'caution'. This part of the gauge conversion work took place over the weekend of Saturday/Sunday 11/12 May 1872 and the first standard gauge train ran on the South Wales line on Monday 12 May. The line to Ross and Hereford had of course already been converted by 1872 (in 1869) and how the section between Grange Court and Gloucester was operated in the interim is unclear. It may have been mixed gauge on both tracks or it may have been operated as two single lines of different gauges. The other 1872 photograph shows a crossover between the siding and the Hereford line, suggesting at least one of tracks between Grange Court and Gloucester was temporarily
of mixed gauge
Photo courtesy Great Western Trust Photo Archive

Looking south-west on an unknown date in the early years of the twentieth century and certainly after 1896 as the original and lofty West signal box has disappeared. The platforms, which are still oil lit, must have been quite pleasant with the bushes and other enchantments. Behind the station on the left is the rather forbidding-looking stationmaster's house, extant at the time of writing. Part of the building on the far, Down South Wales, platform is also extant.
Photo from John Mann collection

Click here for Grange Court Junction: Gallery 2
Before 1935 - c1950

 

 

 

[Source: Darren Kitson]




Last updated: Friday, 18-Apr-2025 16:46:01 CEST
© 1998-2025 Disused Stations