Station Name: DOVER MARINE/DOVER WESTERN DOCKS

[Source: Nick Catford]


Date opened: 18.1.1919 (opened for military use 2.2.1915)
Location: On the Admiralty Pier accessed from The Viaduct (the end of the A20)
Company on opening: South Eastern & Chatham Railway
Date closed to passengers: 25.9.1994 (unadvertised passenger trains continued until 19.11.1994)
Date closed completely: 19.11.1994
Company on closing: British Rail (Southern Region)
Present state:

The station is a listed building and is in use as a cruise terminal. The trainshed is largely unaltered externally and internally still retains many of its original buildings and features.  The station entrance building opposite the Lord Warden hotel and the footbridge linking it to the trainshed are included in the listing. This is still the public access to the Admiralty Pier.

County: Kent
OS Grid Ref: TR322402
Date of visit: January 1995 & March 1996
Notes: Continuous traffic growth in the later years of the nineteenth Century underlined the need for improving the Admiralty Pier which was open to the elements. The plans for Admiralty Pier were amended in 1906 to allow the building of a new station for the South Eastern & Chatham Railway on reclaimed land on the north side of the pier. This would replace the existing station on the Pier which was always susceptible to closure during heavy seas.

Dover Harbour, which is generally acknowledged to be one of the greatest feats of port construction at that time, was completed in 1909. The walls and piers were built of large blocks weighing from 30 to 40 tons. These blocks were made of concrete, with a granite facing to those that were to be placed on the outside surfaces of the walls above water level. The completed harbour was opened on 14 October 1909 by H.R.H. the Prince of Wales, the future King George V. In 1909 work started on the new station to create an artificial platform for the new terminus alongside the north end of the Admiralty Pier.

Creating sufficient land for the new terminus involved the construction of a sea wall made out of concrete blocks to the east of the Admiralty Pier. Large quantities of chalk were then dumped into the water between the pier and the new wall with the pier becoming the western side of the new station site.  1,200 ferro-concrete piles were manufactured on site; up to 75 feet in length and seventeen inches in diameter. These were driven down through the chalk into the original seabed; this process avoided having to wait for the dumped chalk to settle. The heads of the piles were connected by re-enforced concrete slabs.

Once the reclamation of the 12 acres site had been completed construction of the terminus started in 1913. It comprised a steel and glass cathedral roof (trainshed) 800 feet in length and 170 feet wide. Beneath the trainshed there were two 60-foot wide concrete island platforms, each 693 feet in length.

The station was largely completed in 1914 but with the start of WW1 the continental ferry service ceased to operate as wartime economy measure. Dover Town station closed on 14 October 1914 with all services being diverted to Dover Harbour and Dover Priory. Admiralty Pier and the new terminus were taken over for military use with the new station opening as Dover Admiralty Pier, for military traffic only on 2 January 1915 when it became the principal ambulance railway station. During the early years of the war the station was still in an unfinished state.

From January 1915 onwards the port of Dover was the main evacuation port for wounded soldiers. Between January 1915 and February 1919 it is estimated that 1,260,000 wounded and ill soldiers passed through the port and were dispatched to all parts of England, Wales and Scotland from the station. From July 1917 overseas leave and draft men were conveyed to the Western Front via the port of Dover. These additional troop movements continued unabated until February 1919 when the facilities in Dover were finally turned over to the civilian authorities.

Repatriated British prisoners of war started to arrive at Dover on 17 November 1918. By February 1919 180 boats conveying 55,398 released former POW’s were received by 130 trains. In January 1919 the large Customs Examination Shed in the station was utilised for the sorting out of demobilised men, who began to arrive at Dover in large numbers. The numbers passing through Dover amounted to 720,664 service men. When the armistice came in November 1918, the SE&CR had a fine record of war service to its credit, and Field Marshall Sir Douglas Haig wrote the following letter of commendation to Cosmo Bonsor, the Chairman of the SE&CR Managing Committee; ‘The Army in France owes much to all connected with the control of our railway companies in the United Kingdom, and indeed in the Empire. They have at all times shown great willingness to help us in every possible way in their power. Track has been torn up to give us rails, engines, trucks, men, capable engineers, operations staff all have been sent abroad to us, regardless of their own special needs and demands of the people at home, and without a moment’s hesitation. But we have been more closely associated with the South Eastern and Chatham Railway than any other. The bulk of our ammunition and stores required for the maintenance of our armies, as well as several millions of men as reinforcements and on leave, have passed over their system. Their sphere of duty, too, has been nearest to the shores of France and Belgium, and consequently more open to hostile attacks by air and fear of invasion by sea. Undisturbed by any alarms the traffic for the Armies in France has never ceased to flow. This reflects the greatest credit on all concerned with the company’.

Much of the north end of Admiralty Pier was incorporated into an extensive network of trackwork and sidings around the new station; these were required to handle the large quantity of freight traffic passing through Dover during the war. Access to the station and sidings was controlled by a large 120-lever SE&CR designed signal box on the down side approach to the station. The two platforms were spanned by a lattice footbridge at the north end of the trainshed.

Although the trainshed was virtually complete, construction of the stone façade at the north end had not been started. Once completed this comprised an ashlar frontage with rusticated dressings. The central section had a large central round-headed opening for two tracks with rusticated surround and enriched keystone with the inscription above 'S E and C R'. There were flanking full-height narrow rusticated arches within which were high circular windows above pedestrian entrances. The rusticated surrounds rose to an interrupted cornice with blank cartouches in the parapet. The flanking lower bays had rusticated round headed arches and end quoins each for a single track. The sides and rear of the building were of red brick with some ashlar dressings. The south-east elevation had pilasters at regular intervals and some black brick dressings. Pedestrian access was through a detached entrance block opposite the Lord Warden hotel.  This comprised a tall three-bay single-storey building with doorways flanking a central window. The north-west side, facing the hotel, had patterned stonework with quarry faced quoins. The three openings had stone arching (voussoirs). There was a decorative cornice with slate French pavilion roof and a circular window. The return bays had round-headed windows flanked by rusticated engaged Tuscan columns and the remainder was of brick with stone dressings. A wide stairway led up to a 455-foot long enclosed glazed footbridge which was suspended above the double-track of the former Admiralty Pier. The footbridge was divided down the middle with cast iron railings to separate people going on to the pier who use the west side while  passengers for the station used the east side. The sides of the walkway were constructed of steel with elliptical roof trusses and had continuous windows.

On each platform there were three large blocks of brick buildings, each 100 ft in length and 25 ft in width. These buildings were allocated to a variety of purposes, including waiting rooms, tea rooms, dining and refreshment facilities, post and parcel shed railway staff rooms etc. At the end of each platform nearest to the Admiralty Pier provision was made for a Post Office, and at the end of the other platform there was a Customs Examination and Clearance Shed.

After WW1 the SE&CR erected a war memorial on the platform in tribute to the 5,222 staff and employees of the South Eastern and Chatham Railway who served in HM forces War. Of those who served 556 men lost their lives.

A 4-road carriage shed which was open at both ends, was built on the west side of the trainshed, it was 700 feet long by 63 feet wide and intended for cleaning carriages and the minor servicing of locomotives. It was a notoriously unpleasant place to work, especially in southwest gales at high tide. On such occasions the waves would come over the pier parapet, cross the open tracks and pour down through the various holes in the roof. In later years the salt water would often cause an electrical short circuit on the insulator pots under the conductor rails which then sometimes exploded! The shed could be entered through a doorway in the trainshed wall.

With the restoration of continental services after the war the new station was renamed Dover Marine in 1918 and opened for passenger traffic with the first boat train arriving on 18 January 1919.  In 1926 Admiralty Harbour was recognized to have limited military use and it was decided to hand it, including the Admiralty Pier, to the Dover Harbour Board for administration as a commercial undertaking. The only facilities for locomotives were a turntable and water tank sited behind the signal box.

On 14 November 1924 the 'Continental Express' boat train was introduced and consisted of the six first class Pullman cars, a baggage and brake van. It left London Victoria at 10.50 am, the return  'Continental Express'  train leaving Dover for London at 5.30 pm.

The Southern Railway introduced the Golden Arrow service on 15 May 1929. They had already introduced the Continental Express boat train on 14 November 1924 that was designed to give extra comfort. That train consisted of six first class Pullman cars, a baggage and a brake van and left London Victoria at 10.50hrs with the return Continental Express train leaving Dover for London at 17.30hrs. The French, in September 1926, followed Southern’s lead and launched an all-Pullman train between Paris and Calais, giving it the title of ‘Fléche d’Or’. To take passengers across the Channel, Southern had ordered the Canterbury from William Denny & Brothers of Dumbarton. In the meantime, the company decided to upgrade the Continental Express with a new train given the anglicised name of the ‘Golden Arrow’.



The ‘Golden Arrow’ consisted of 10 Pullman cars, hauled by a 4-6-0 Lord Nelson Class or King Arthur class engine sporting a Union Flag and Tricolour. At the time the Lord Nelson class was introduced, in 1926, they were the most powerful engines in Great Britain. The carriages were individually named, resplendent in chocolate and cream and aimed exclusively at first-class Pullman passengers. On board was the ‘Trianon’ cocktail bar, a converted twelve-wheeled Pullman, modeled on a high-class club for the rich. The train also boasted of the first public address system and passengers were addressed in both English and French.

The Canterbury was launched on 13 December 1928 at Dumbarton and arrived in Dover on 30 April 1929 and commenced service on 15 May, the same day as the ‘Golden Arrow’. The journey between London and Paris was advertised to take 6½ hours and each day the ‘Golden Arrow’ was scheduled to depart London Victoria at 11.00hrs and reach Dover Marine station at 12.38hrs. As the line is fairly level with a very long straight section, speeds of 60 mph were not unknown. Having crossed the Channel in the Canterbury and on reaching Calais the passengers were transferred to the awaiting ‘Fléche d’Or’, a four-cylinder Nord Pacific of the French Northern railway, arriving in Paris at 5.35pm UK time. The single fare was £6.10s.

When the original Cross-Channel sleeper service was introduced in 1869 passengers were required to catch the train in London, alight in Dover at the Admiralty Pier, embark on the night sleeper ferry, disembark at the Continental port and then catch a train to Paris or Brussels.

To run a service where that passenger could stay in the same compartment between London and a Continental capital without alighting was problematic due to Dover’s tides. The maximum difference between high and low tides at Dover is some 23-feet; however, by the 1920s advances in technology appeared to make such a service possible. Southern Railway, in the UK and the Société de Navigation Angleterre-Lorraine-Alsace in Belgium agreed to build a train ferry dock in Dover, outside the Tidal Basin, between South Pier and Admiralty Pier a short distance to the north-east of Dover Marine station.

The specifications, drawn up by George Elson, Chief Engineer of Southern Railway, was a concrete dock 414-feet long and 72-feet wide, with a minimum depth of water of 17-feet to a maximum of 36-feet. Construction work started in August 1933 and two railway lines were laid to connect the dock to the main line into Dover Marine. The Southern Railway commissioned three purpose built ferries from Swan, Hunter & Wigham Richardson of Newcastle-on-Tyne. Each ship was designed to take 12 sleeping cars, 500 passengers during the day, or approximately 40 goods wagons. There was also a small floor above the train deck to accommodate approximately 20 cars.

On 28 September 1936, the first trains were shunted aboard the ‘SS Hampton Ferry’ which was decorated with flags and bunting for the opening of the terminal with many distinguished guests making the return crossing to Calais. The night service between London and Paris was officially inaugurated by the French Ambassador on 5 October 1936. The train left Victoria Station at 11pm and arrived in Paris at 8.55am the following day. The counterpart left Paris for London and there was a daily goods service via the ferry.  A new daily service was launched during the night of 5 October 1936. The 'Night Ferry' was an international sleeper train between London Victoria and Paris Gare du Nord (and later also Brussels). It was operated jointly by the SNCF and the Southern Railway

Facilities for the shipment of cars to and from the Continent by the train-ferry service were launched on 28 June 1937, when a ramp connecting the shore with the steamer was used for the first time. 

On 14 January 1939 Neville Chamberlain together with Lord Halifax, foreign secretary, travelled by way of Dover Marine, using the ‘Golden Arrow’ and the ‘Canterbury’, for Rome. This was to meet with Benito Mussolini, Italian prime minister and leader of the National Fascist Party, in an effort to persuade him not to become involved in the pending conflict. World War II was declared on 3 September 1939. Following the ‘Golden Arrow’s’ last trip, the ‘Canterbury’ left Dover for conversion into a troop carrying ship. The ship ‘Invicta’ was built in 1939 to take over from the ‘Canterbury’ but she was also commandeered for war work following her launch in 1940.

Although the ferry service was once again curtailed the station remained operational handling hundreds of special trains during the Dunkirk evacuation.  On peak days, some 60,000 men boarded special trains. All told nearly 200,000 British and Allied troops passed through Dover. Consistent shelling made it unsafe for the station to handle any kind of passenger traffic. On 12 May, during the evacuation, the town and port was declared a ‘Protected Area’ and following the evacuation Marine Station was closed with passenger services along the former SER route into Dover terminating at Folkestone. In June 1941 the station was re-opened to military traffic going to the Second Front following Germany’s invasion of Russia. On 7 June 1940 the engine shed near Marine station received a direct hit with one serious injury. The Marine Station came in for sustained shelling and on 25 September and on 12 September 1944 there was substantial damage to the roof during an air raid.



After the war the Marine station was handed back to Southern Railway and another plaque was added to the station’s war memorial stating: 'And to the 626 men of the Southern Railway who gave their lives in the 1939-1945 war. The passenger ferries returned; on demobilisation, the ‘Invicta’ was converted to oil fuel having been originally designed to use Kent coal. She was fitted with radar and on 10 October 1946 came to Dover to take over the ‘Golden Arrow’ service. Pre-war passenger numbers were never regained due to the popularity of the car and when new car ferry services were introduced the number of rail passengers using the ferries dropped dramatically.

To accommodate 12-car multiple-unit trains when the electrification from London via, Faversham started in June 1959, the two island platforms at Dover Marine were extended by 114 feet, with 24-foot ramps. The extensions comprised prefabricated concrete components, manufactured at Exmouth Junction concrete works. This necessitated altering the layout of the tracks at the London end and the construction of a riveted steel footbridge across the approach tracks from Dover Priory, linking the main entrance beside the Lord Warden Hotel with the Customs Hall, on the northern perimeter of the Western Docks. The bridge ran from the landing at the top of the stairs from the street entrance opposite the Lord Warden hotel.

During this work, the station was closed for one week at the end of February 1959, and was re-opened on 1 March. During that period, cross-Channel services were diverted to Folkestone, apart from the car and train ferries, which worked as usual as the tracks to the train ferry dock were not affected. By the end of the week, track work had been completed, and the spans of the footbridge erected. The full width of the extended platforms between tracks 3 and 4 and tracks 5 and 6 was provided with a W shaped canopy without a valance for weather protection as it was outside the trainshed.  A relay room was built alongside the signal box for the colour light signals that were brought into use with the electrification.

Steam trains were still seen at the station after electrification as the Folkestone line wasn't electrified until 18 June 1962. Despite the new electrified service in face of further stiff competition from the car in the 1960s, the Invicta made her last ‘Golden Arrow’ sailing on 8 August 1972 and the last ‘Golden Arrow’ train ran on 30 September that year.

Dover Marine was renamed Dover Western Docks on 14 May 1979 and although its future seemed secure the ‘Night Ferry’ was withdrawn on 31 October 1980.  By this time the carriages were dated and in need of replacement; they were not air conditioned, and during the ship voyage, while inside the ship, they became notably hot in summertime. This was exacerbated by the chaining of the vehicles to the ship's deck, an activity underneath the sleeping compartments which inevitably woke most passengers up during the middle of the night. The carriages were over 40 years old, and by some margin were the oldest passenger vehicles running on the British network.

By mid-1985 the rails in the trainshed had been cut back at the south end to create a ground level passenger walkway behind the new buffers. A headshunt was however retained until 1992.  Although the ferries were still well used at this time, when the first Channel Tunnel boring began on 1 December 1987 it soon became clear that the station's days were numbered. Closure of the station was announced in a BR report published in 1989 titled 'Proposed closure of Dover Western Docks Station and Folkestone Harbour branch'.  It was clear from the report that passenger ferries were an outdated mode of transport as the Channel Tunnel would be able to cater for all passenger requirements with a much faster and more efficient service.  Any freight that couldn’t be handled by the tunnel such as chemicals and inflammable products would be transferred to the non-rail connected Eastern Docks.



On 25 September 1994 Dover Western Docks station was closed following the completion of the Channel Tunnel and concentration of remaining Dover ferry services on the Eastern Docks. After 'official' closure the station continued to be used by unadvertised passenger trains to Faversham until 19 November 1994 after which date they were classified as empty stock movements. After closure the station remained in operational use for train berthing and cleaning purposes.  All rail movements finally came to an end on 5 July 1995 with the closure of the signal box.

Demolition and track lifting began at the beginning of 1996. The Dover Harbour Board had hoped to demolish everything to build a new cruise terminal but the trainshed and the entrance building on Lord Warden Square were Grade II listed by English Heritage on 22 June 1989 so the only demolition related to the platform extensions that had been added in 1959.

The trainshed was converted into a cruise liner terminal; this included filling the trackbed up to platform level to create car parking.  All the buildings within the trainshed were retained as was the covered footbridge to the pedestrian entrance. Although not part of the listing the signal box was also retained as offices although it was eventually demolished in 2000.

Dover's £10 million Cruise Terminal (now known as Cruise Terminal 1) was opened in June 1996 by the Chairman and Chief Executive of Cunard Line during a visit by the Royal Viking Sun. Dover Cruise Port is the second largest cruise port in the UK and in 2006 carried approximately 190,000 passengers travelling with 37 different cruise lines. 

Along with the removal of much of the old railway infrastructure at Dover Western Docks in 1979, the ‘Night Ferry’ enclosed dock was filled in and is now used as an aggregates terminal. An attempted resurrection of British–Continental sleeper services under the Nightstar (a play on Eurostar) brand after the opening of the Channel Tunnel in 1994 was abandoned after many of the coaches (night coaches, sleepers, and food service cars) for it had been built. Competition from cheap airlines in the 1990s meant the service could never be profitable, and the proposed service faced daunting logistical issues as well. The coaches were never used in Europe; they were sold to Canada's Via Rail.

Route maps drawn by Alan Young. Tickets from Michael Stewart except 0068 and 2590 Brian Halford. Bradshaw from Nick Catford.

Special thanks to the Dover Historian web site for help with this feature.

Click here to see a film of a train journey between Folkestone Junction and Dover Priory in the 1920s.

Sources:

See also: Folkestone Harbour, Folkestone East, Folkestone Warren Halt, Shakespeare Cliff Halt, Archcliffe Junction Staff Halt, Dover Town, Dover Harbour, Dover Marine (Western Docks) & Dover Admiralty Pier

Dover Marine Station Gallery 1: 1911 - April 1914

In 1911 Work is underway to reclaim sufficient from the harbour before construction of the new station can start. This involved creating a sea wall of concrete blocks to the east of the Admiralty Pier. Huge quantities of chalk were then dumped into the water between the wall and the pier. The former LC&DR line to the Admiralty Pier is seen in the foreground. In the distance two lighthouses are seen on the left, the closer is on the Prince of Wales pierhead; the more distant lighthouse
is on the Southern Breakwater.
Copyright photo from John Alsop collection


Track layout around Dover Marine during WW2. Note the military platform to the north-east of the loc shed, this is a remnant of the former Dover Town station platform. Click here for larger version.

Plan of Dover Marine station in 1959 before the platforms were extended prior to electrification.
Click here for a larger version.

Dover Marine station during construction in October 1911. The land for the station was reclaimed from the sea and was created by dumping large quantities of chalk into the water and then driving 1,200 ferro-concrete piles through the chalk into the seabed below. The piles which were up to 75 feet long and seventeen inches in diameter were manufactured on site as seen in this view. Driving in the piles was completed in 1912.

Dover Marine station under construction looking north c1913. The metal framework of the trainshed has been completed. The platforms have been built and some platform buildings are seen. The west side wall of the trainshed is partially built.


The construction site seen from the Admiralty Pier in April 1914. The station and the adjacent carriage sheds are seen in this view.
Photo from John Mann collection

Click here for Dover Marine Station Gallery 2:
10 November 1920 - c1950s


On 10 November 1920, the coffin holding the body of the Unknown Warrior was taken to Boulogne where HMS Verdun lay waiting to bring him home to Britain. As HMS Verdun approached Dover, the Prince of Wales Pier was overflowing with people who had come to pay their respects. The town’s shops had closed, and flags were flown at half mast. Six bearers, Lieutenant-Colonels or the equivalent rank from all of the armed forces, boarded the ship, and the coffin was received by General Sir J. Longley, Commander of the Eastern Area, and Colonel Knight, Commander of the Dover Garrison. The party processed to the western platform of the Marine station, from which the train to London was due to leave at 5.50pm. A plaque now commemorates the Unknown Warrior’s home-coming. The coffin was placed in passenger luggage van No.132 of the South Eastern and Chatham Railway Company, the same van which had carried the bodies of Nurse Edith Cavell and Captain Charles Fryatt. From Dover Marine station the Unknown Warrior was to London for burial the following day at Westminster Abbey.

Dover Marine station looking north from platform 5 in 1921 two years after the station opened to the public. There were two 60-foot wide island platforms numbered 3 and 4 and 5 and 6. Roads 1 and 2 did not serve platform faces and were outside the trainshed and were used by trains loading goods directly onto ships.
Photo from Jim Lake collection

The only locomotive facilities at Dover Marine were a turntable and water tank behind the signal box; they are seen in this view from the 1920s. Locomotives were allocated to the former LC &DR shed at Dover Priory. This was replaced by a new 5-road shed on the site of Dover Town station in 1928. The turntable and tank seen here were removed at this time.
Photo from John Mann collection

Dover Marine station seen from the Lord Warden hotel before August 1923. The covered footbridge from the pedestrian entrance is seen on the right passing over the lines to the Admiralty Pier. The width of the two island platforms is clearly seen in this view
Copyright photo from John Alsop collection

Looking south towards Dover Marine station in May 1925. The pedestrian entrance opposite the Lord Warden Hotel is seen on the right. From there a 455-foot long enclosed glazed footbridge too passengers into the station. Dover Marine's 120-kever signal box is seen on the left.
Copyright photo John Alsop collection

The rail entrance to platform 3 at Dover Marine station in 1928. The ship berth, served by two railway tracks is seen on the left. 'Lord Nelson' class 853 is seen. This loco entered SR service in September 1928 and was named Sir Richard Grenville after the famous Royal Navy Admiral. Built at Eastleigh works to a design by Richard Maunsell and fitted with smoke deflectors in the late 1920s, it also benefitted from modifications by Bulleid when he took over from Maunsell as Chief Mechanical Engineer in 1938. Renumbered to 30853 by BR in 1948, it was withdrawn from 71B, Bournemouth shed on 3 March 1962 and scrapped very soon afterwards
Copyright photo John Alsop collection

The 11am boat train from London Victoria is seen passing Dover Town station on the approach to Dover Marine on 16 June 1924. This train is the predecessor of the 'Golden Arrow'. 497 was built at Ashford Works to a Harry Wainwright E Class design entered service in September of 1907. This loco was rebuilt in the early 1920s by Maunsell with a larger boiler, firebox and cylinders and renumbered by the Southern Railway to 1497. It was finally withdrawn by BR from 73B, Bricklayers Arms shed numbered 31497 on 22 October 1960 and broken up later that year. It was involved in a crash on 5 March 1909 when it overran signals at Tonbridge Junction, Kent whilst hauling an express passenger working and loco 165 that was hauling a mail train, ran into it killing two and injuring eleven.
Photo from John Mann collection

Dover Marine station looking north from platform 4 c1930s.
Copyright photo John Alsop collection

The approach to Dover Marine station c1933 during the construction of the train ferry dock. Initially a sheet metal cofferdam with an earth embankment was constructed but this was washed away during the winter of 1933/4 after which 10-ton concrete blocks were laid on foundations on the seabed.
Photo from Jim Lake collection

Looking north towards Dover Marine station from the Admiralty Pier c 1930s. The Dover Turret is seen on the left. This fort, at the the ten end of the Admiralty Pier, was completed in 1880 and mounted with two 16in, 81-ton rifled muzzle loading (RML) guns with a range of 4.3 miles. The Grand Shaft barracks on top of the Western Heights, is seen in the background.


During WW2 the Marine station was prone to consistent shelling and was closed after the Dunkirk evacuation. On  7 June 1944 Southern’ Railway's engine shed near Marine Station received a direct hit seriously injuring Henry Whitewood, who died a week later. The worst damage to the Marine station occurred overnight on 12 September 1944, luckily most of the damage was confined to the roof. Note the lack of any kind of signage. By this time All trains and stations, by this time,Dover subject to the blackout. Station names were removed so passengers had to rely on a porter shouting out the name. At night, as most station lights were sprayed with blue paint, platforms were sparsely lit and even that was extinguished when the air raid warning was sounded.

The north end of the Dover Marine trainshed in August 1947. The photographer is standing beneath the long footbridge that links the passenger entrance opposite the Lord Warden hotel with the train ferry dock. In the distance the Prince of Wales pierhead is seen and beyond that the Southern Breakwater.
Photo from John Mann collection




Dover Marine station and the Admiralty Pier seen from the Western Heights in circa 1950s. The original pierhead is seen top centre with the early 20th century extension to the left. The Dover Marine trainshed is seen in the centre with the four-road carriage shed to the right. The building at the south end of the trainshed is the customs hall. The train ferry dock is seen bottom centre, pedestrian access is by footbridge on the north side of the Lord Warden hotel. By the end of the decade this footbridge would be joined to the footbridge to the Marine station with a new section of bridge running along the east side of the hotel. The building to the right of the hotel is part of Dover Town station. In the 1930s the building was used as offices for the Southern Railway Marine Department. It is not known when they left but the building survived until 1963.

Click here for Dover Marine Station Gallery 3:
Mid 1950s - September 1969





Storm damage at Dover Marine circa mid 1950s; the carriage shed is seen in the background. The Admiralty Pier has always suffered during bad weather. When the pier was under construction, on 8 October 1850 an intense storm, centred on Dover, destroyed much of the works. Piles, 18in square, were snapped and three huge diving bells were carried away to sea. At daybreak the bay was strewn with fragments of timber and machinery including broken cranes, air-pumps and traversers.


Dover Marine station in early 1959 during construction work to extend the platforms by 114 feet prior to electrification London (via Faversham) line in June that year. During the work stat station was closed for a week at the end of February, reopening in 1 March 1959. The work also involved some changes to the track to accommodate the platform extensions.

Battle of Britain 4-6-2 No. 34071 '601 Squadron' at Dover Marine station in February 1960. This view shows the prefabricated concrete extensions to the platforms and the plain W shaped canopy. 601 Squadron was designed by Bullied and built at Eastleigh works in October 1945. Three months after this photo was taken, 34071 was rebuilt at Eastleigh and stayed at Eastleigh shed until withdrawal after just 19 years of service on 30 April 1967 to be cut up at Cashmores of Newport five months later.
Copyright photo by Alan Lewis Chambers from his Railway Images web site

Dover Marine station in 1960. The passenger entrance can just be made out top left, opposite the Lord Warden hotel. From that, two footbridges are seen. one runs along the east side of the hotel to the train ferry dock which is seen to the right of the hotel. The other is in line with the Admiralty Pier and then turns sharply to the east to enter the Marine station near the north end of the trainshed. This then joined up with an internal footbridge spanning the platforms. On the west side of the trainshed the curving four-road carriage shed is seen. The original pierhead with the gun turret is seen bottom left. The pier was widened here and extended in the first decade of the 20th century. Click here for a larger version.

Working the 'Golden Arrow' out of Dover Marine circa early 1960s is 70004, 'William Shakespeare, a Riddles designed Britannia Pacific. Delivered new to 30A, Stratford shed on 29 March 1951, it was polished up and given a special finish to appear with the new Golden Arrow Pullmans at the Festival of Britain Exhibition between May and September of that year. Transferring to 73A, Stewarts Lane Shed in the October, it became well travelled in the 60s with Trafford Park, Willesden, Aston, Crewe North and Stockport sheds to it’s name, finally being withdrawn on 30 December 1967 from 12A, Carlisle Kingmoor and cut up during March the following year by T.W.Ward of Iverkeithing.
Photo from Jim Lake collection

Passengers boarding the Golden Arrow at Dover Marine station circa early 1960s.

The approach to Dover Marine station from the Folkestone direction in the Early 1960s. The platform extensions are clearly seen with their plain W shaped canopies. The footbridge to the pedestrian entrance opposite the Lord Warden hotel is seen in the foreground.
Photo from John Mann collection
Platforms 4 (left) and 5 at Dover Marine station seen from the footbridge in the 1960s.
Photo from John Mann collection

The 'Golden Arrow; is seen approaching Dover Marine station in the 1960s. In 1961, with the Kent Coast electrification scheme, the service became electric-hauled. This allowed an acceleration to 80 minutes for the down service and 82 minutes for the up service. Twenty-four electric locomotives were built in 1958 for the Kent Coast main lines. They were built at the British Rail workshops in Doncaster. Class 71 E5015 is seen here passing under the passenger footbridge before entering the station.
Photo from Jim Lake collection

The 'Night Ferry' is awaiting departure from Dover Marine to London Victoria in the 1960s. When the train arrived at Dunkirk the it was split into sections and loaded equally on tracks on the port and starboard sides of the ship, to maintain its balance. The coaches were chained to four parallel lines on the deck. Each overnight train carried up to five (very occasionally six) sleeping cars plus baggage cars. On arrival at Dover, the coaches were shunted to the Marine station where a waiting class 73 electro-diesel was ready for the final leg of the journey to Victoria. In the old days, the 'Night Ferry' was was the only service of the Southern Railway to be regularly double-headed, with a Bulleid Pacific and E1 or L class 4-4-0 locomotives. The train was not a good timekeeper because of the complexity of loading
and offloading coaches
Photo from John Mann collection


A class 71 is seen at Dover Marine station in June 1969. This class of locos 2700 power was useful for heavy freight and express passenger work. Acceleration on passenger trains (even when heavily loaded) was quite astonishing - to the extent the climb out of London Victoria was almost unnoticeable . Prestigious services including the 'Night Ferry' (London to Paris overnight by train-ferry) and the 'Golden Arrow', were a mainstay of the class for many years.
Photo by Terry Tracey

Looking north from the road to the train ferry dock in June 1869. Dover Marine station is behind the photographer. The clock tower of the closed Dover Harbour station is seen in the distance.
Photo by Terry Tracey


Looking north from the north end of Dover Martine station in September 1969. The shows the rear of the entrance building from where two footbridge run from the landing at the top of the stairs. That on the left is the original bridge running into the Marine station, that on the right leads to the train ferry dock. The Lord Warden hotel dominates the background. Note the warning signs in three languages.
Photo by Bob Bridger from 30937 Transport Photograph Database

Click here for Dover Marine Station Gallery 4:
September 1973 - August 1993






The street level passenger entrance opposite the Lord Warden Hotel in September 1973. There is a wide stairway up to the footbridge inside the building, both the stairway and the footbridge are divided down the centre with cast iron railings. The sign above the door on the left says 'Dover Marine - Trains and Ships' while that on the right says 'Promenade and fishing only'. The footbridge on the left runs to the train ferry dock. The 120-lever Marine signal box is seen below the bridge.
Photo by John Mann

Dover Marine station in September 1973. The ferry dock footbridge has suffered badly from the bad weather and has been strengthened. With the withdrawal of the 'Night Ferry' on  31 October 1980 the dock's days were numbered and it finally closed 8 May 1987. This bridge was quickly demolished.
Photo by John Mann

Looking north along platform 5 at Dover Marine station on 31 July 1976 during a visit by the Lea Valley Railway Club's 'Sunny South Express' railtour. The tour was a round trip from Charing Cross with DEMU 1034. A number of closed passenger lines were visited including Tilmanstone Colliery on the East Kent Light Railway and Ardingly on the electrified link to the Bluebell line and Lavant.
Photo by Alan Young
The 4-roqad carriage shed at Dover Marine station in January 1978. Two 4-CEP units are seen in the shed with a class 33 alongside. The Admiralty Pier is seen curving round on the right. Before Dover Marine opened the two original platforms at Admiralty Pier were beneath the promenade. The roof of the customs hall is seen in the background.
Photo by John Law from his Flickr photostream

Night Ferry Type F sleeping car in the traditional colours of the CIWL (Compagnie Internationale des Wagons-Lits) just having arrived at Platform 4 at Dover Western Docks in the late 1970's. Type F sleeping cars have passenger access doors at one end only. The door space at this end contains an attendant's office and opposite is a compartment for a boiler.
Copyright photo from Eastbank Model Railway Club web site

Class 410 (4-BEP) 7005 stands at platform 5 at Dover Western Docks station in 1982. British Rail Class 411 electrical multiple units were built at Eastleigh works from 1956-63 for the newly electrified main lines in Kent. A variant of the class 411 design was the class 410 which contained a buffet car in place of a standard trailer.


The Orient Express hauled by a class 73 and diverted from Folkestone Harbour is seen at Dover Western Docks station in 1982. The Venice Simplon-Orient-Express, or VSOE, is a private luxury train service from London to Venice and other European cities. The VSOE has separate carriages for use in the UK and for continental Europe, but all of the same vintage (mostly dating from the 1920s and 1930s). Restored Pullman carriages are used in the UK and over the channel restored dark blue former Compagnie Internationale des Wagons-Lits carriages are used. These days, passengers are conveyed across the English Channel by coach through the Channel Tunnel.
Photo by John Law from his Flickr photostream

21 September 1985 saw the Metropolitan Railway electric locomotive No. 12 'Sarah Siddons' work the London Regional Transport/British Rail 'Romney, Hythe & Dymchurch Railtour' around Kent. The train started at Victoria and ran via Swanley and Tonbridge to Folkestone West, from where passengers were taken for a trip on the Romney Hythe and Dymchurch Railway. The tour restarted from Dover Western Docks and ran via Faversham and Eltham to London Bridge. 'Sarah Siddons; is seen
at Dover Western Docks.
Photo by Richard Allen from his Flickr photostream
4-CEP EMU set 1583 departs Dover Western Docks leading service 1P46 the 13.47 Dover Western Docks to London Victoria in August 1987. On the right stands immaculate 47 621 then named 'Royal County of Berkshire' waiting departure with 1M04 the 13.55 to Liverpool Lime Street. The vessel on the left moored alongside the quay was the RMT 'Jetfoil lounge' a floating pontoon vessel where passengers waited before joining the Jetfoil service to Ostend in Belgium.
Photo by Adrian Nichols from his Flickr photostream

47527 passes Dover Ferry sidings with 1M04 13.55 Dover Western Docks to Liverpool Lime Street
on 20 April 1988.
Photo by Graham Walker from his Flickr photostream

Four months later everything had changed, this the the Dover Ferry Dock (seen in the picture above) in August 1988 after the track was lifted. The dock It was taken out of use in 1987-88 when the new train ferry built for SNCF the 'Nord Pas-de-Calais' was introduced to the Dover to Dunkerque route. Being a much larger vessel it used a new link span located beyond Dover Western Docks station beside the southern breakwater.
Photo by Adrian Nichols from his Flickr photostream

The old train ferry terminal and customs shed at Dover Western Docks in August 1988.
Photo by Phil Mackie

1
By August 1993 the station's days were numbered; a year later it would close. Network Southeast
4-CEP unit No. 1520 departs Dover Western Docks at the rear of the 14,35 Boat Train to Victoria
Photo by Brian Creasey
 

Click here for Dover Marine Station Gallery 4:
August 1993 - June 2012




Network Southeast 4-CEP units Nos. 1566 and 1581 stand at Dover Western Docks on in August 1993.
Photo by Brian Creasey

Network Southeast 4-VEP unit No. 3184 departs Dover Western Docks working a stopping service to Victoria via Chatham on the 21st August 1994, a month before closure
Photo by Brian Creasey

The 'Continental Farewell' railtour from London Victoria is seen at Dover Western Docks station on 25 September 1994. This tour featured ex-BR Pacific 70000 'Britannia' (but presented on this occasion as 70014 'Iron Duke' which was one of two Britannia class locomotives regularly used on the 'Golden Arrow' service in the 1950s). This was the last day of use at Western Docks, the station having closed to regular passengers the previous day. There were also 2 mini-tours (The Kentish Wanderer A and B) with HA E5000 series E5001 (seen left) that ran with the stock off the main tour. It ran via Canterbury West, Ashford and Folkestone.
Photo by Andy Veitch from his Flickr photostream

As the evening draws in on 25 September 1994 the railtour prepares from the return journey to Victoria.
Photo by Andy Veitch from his Flickr photostream

Dover Western Docks Station in January 1995, 3 months after closure. After 'official' closure the station continued to be used by unadvertised passenger trains to Faversham until 19 November 1994 after which date they were classified as empty stock movements. In January 1995 the station was still being used for train berthing and cleaning.
Photo by Nick Catford

Dover Western Docks entrance in January 1995, the sign above the door has been removed but the door is still open.
Photo by Nick Catford

Looking north towards Dover Docks station from the Admiralty Pier in March 1896. Everything south of the trainshed has been cleared awaiting redevelopment.
Photo by Nick Catford
Dover Western Docks station in January 2003. The listed station reopened as a cruise terminal in 1996.
P
hoto by Chris Fletcher

The cruise terminal and Dover Western Docks in 2005.
Dover Western Docks station in 2006, the track bed has been filled up to platform level to create a car park. Apart from this and the lack of signage little else has changed since closure. The four K6 red telephone boxes (two on the platform and two outside the trainshed at the south-west corner)
are also listed.
P
hoto Ted Arnott

Dover Western Docks station in 2006; SE & SC is clearly seen above the arch.
P
hoto Ted Arnott

Dover Western Docks station platform 4 in June 2012. The war memorial is seen on the end of the building, This shows the names of the 356 men of the South Eastern and Chatham Railway who died in the First World War and the 626 men of the Southern Railway who died in the Second World War.
Photo from Nick Catford collection

Dover Western Docks station seen from a cruise liner moored alongside in June 2012.
Photo from Nick Catford collection
Name

Click here for more pictures of
Dover Marine/Dover Western Docks station




10 November 1920

1924

c1920s

Mid 1950s

February 1960

February 1960

Early 1960s

c1960s

c1960s

c1960s

c1960s

c1960s

May 1968

1971

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

September 1973

July 1976

March 1978

Late 1970s

Late 1970s

Late 1970s

Late 1970s

Late 1970s

Late 1970s

Late 1970s

Late 1970s

August 1988

August 1988

August 1988

August 1988

August 1988

August 1988

August 1988

August 1988

August 1993

September 1994

Last day

Last day

Last day

Last day

January 1995

Early 2000s

2006

June 2012

June 2012

June 2012

June 2012

June 2012

June 2012

June 2012

June 2012

June 2012

xxx

xxx

xxx

xxx

xxx

xxx

xxx

xxx

June 2012

Painting

xxx

xxx

Click on thumbnail to enlarge

Click here for more pictures of Dover Marine/Dover Western Docks Station


 

 

 

[Source: Nick Catford]



Last updated: Wednesday, 17-May-2017 10:03:31 CEST
© 1998-2015 Disused Stations